New Delhi: Work on desilting of drains is underway on "war-footing" ahead of the onset of monsoon and it is expected to be completed by June 15, officials said on Friday.

So far, workers have removed more than 87,000 metric tonnes of silt from 688 drains, the Municipal Corporation of Delhi said in a statement.

"The MCD has been working on a war-footing to meet the target of cleaning all the drains under its jurisdiction before the onset of monsoon.

"Taking forward the steps, the corporation has



successfully completed more than 96 per cent work of desilting and all set to complete the work of desilting before June 15," the civic body said in the statement.

Silt taken out from drains is being sent to the landfill site, and its monitoring is being done through RFID tags, it added.

The MCD has also requested PWD, DSIIDC and Irrigation and Flood Control Department of the Delhi government to complete cleaning of drains falling under their jurisdictions before the monsoon, officials said.



No Comments For This Post, Be first to write a Comment.
Leave a Comment
Name:
Email:
Comment:
Enter the code shown:


Can't read the image? click here to refresh

Todays Epaper

English Weekly

neerus indian ethnic wear
Latest Urdu News

Do you think Ruturaj Gaikwad would be a good captain for Chennai Super Kings?

Yes
No
Can't Say