GHMC commissioner R.V. Karnan on Monday inspected the ongoing KBR Park package flyover works near Park Hyatt Hotel at Banjara Hills Road No. 2. 

Accompanied by chief engineer Sahadev Ratnakar, he was informed that excavation for all six pier foundations has been completed, while PCC bed works for three piers are



finished. 

Officials said steel fabrication for raft foundations would begin on Tuesday. Karnan directed Megha Engineering & Infrastructure Ltd., the executing agency, to mobilise additional machinery and manpower to speed up the project. 

He stressed that construction should not obstruct traffic and urged timely completion to avoid inconvenience to the public.
No Comments For This Post, Be first to write a Comment.
Leave a Comment
Name:
Email:
Comment:
Enter the code shown:


Can't read the image? click here to refresh
etemaad live tv watch now

Todays Epaper

English Weekly

neerus indian ethnic wear
Latest Urdu News

Which cricket team is your favourite to win the T20 World Cup 2026?

India
South Africa
New Zealand